Project Location: Pueblo, CO Office
Owner: Public Service Company of Colorado
Contractor: Babcock & Wilcox Construction Co.
In addition to APi insulating the new Unit #3 Alstom 750-MW supercritical coal-fired boiler under a separate contract, APi completed this massive AQCS project for Babcock & Wilcox Construction Company through two separate contracts. The insulation and lagging contract required APi to supply and install more than 433,000 SF of our Type I Prefabricated Insulation Panels, and a small amount of conventional insulation, on the following equipment:
APi also supplied and installed the insulation and jacketing for 10,000 LF of pipe related to the AQCS. Under a second contract with BWCC, APi supplied and installed the industrial siding for the seven SDA penthouse enclosures, two fabric filter penthouse enclosures, and two fabric filter hopper enclosures.