Project Location: Rogers City, MI Office
Owner: Consumers Energy
Contractor: Moran Ironworks
In 2010, APi supplied and installed approximately 50,000 SF of insulation & lagging on a Babcock & Wilcox selective catalytic reduction (SCR) system and the associated ductwork. API completed this work in Moran Ironworks' Rogers City, MI fabrication yard for barge shipment down Lake Michigan to the job site.
In 2013, APi supplied and installed nearly 60,000 SF of insulation & lagging on a B&W Pulse Jet Fabric Filter and the associated ductwork tie-in’s. In addition, API is installed over 50,000 SF of industrial siding on the PJFF enclosures and miscellaneous buildings at site.